Part #1:
- City: Teuchern
- Commissioning:
- 2 turbines: Enercon E138/4200 (power 4 200 kW, diameter 138.25 m)
- Hub height:
- Total nominal power: 8,400 kW
- Operational
- Onshore wind farm
Part #2:
- City: Teuchern
- Commissioning:
- 1 turbine: Enercon E160/5560 (power 5 560 kW, diameter 160 m)
- Total nominal power: 5,560 kW
- Operational
- Onshore wind farm
Part #3:
- City: Teuchern
- Commissioning:
- 5 turbines: Enercon E138/4200 (power 4 200 kW, diameter 138.25 m)
- Hub height:
- Total nominal power: 21,000 kW
- Operational
- Onshore wind farm
Part #4:
- Part: Bauabschnitt
- City: Teuchern
- Commissioning:
- 1 turbine: Enercon E160/5560 (power 5 560 kW, diameter 160 m)
- Hub height:
- Total nominal power: 5,560 kW
- Operational
- Onshore wind farm
Part #5:
- Part: Bauabschnitt
- City: Teuchern
- Commissioning:
- 1 turbine: Enercon E138/4200 (power 4 200 kW, diameter 138.25 m)
- Hub height:
- Total nominal power: 4,200 kW
- Operational
- Onshore wind farm
Localisation
Part #1:
- Latitude: 51° 8' 28.9"
- Longitude: 11° 58' 56.5"
- Geodetic system: WGS84
- Precise localization: no
Part #2:
- Latitude: 51° 7' 52.9"
- Longitude: 11° 58' 35.9"
- Geodetic system: WGS84
- Precise localization: no
Part #3:
- Latitude: 51° 7' 52.9"
- Longitude: 11° 58' 35.9"
- Geodetic system: WGS84
- Precise localization: no
Part #4:
- Part: Bauabschnitt
- Latitude: 51° 7' 52.9"
- Longitude: 11° 58' 35.9"
- Geodetic system: WGS84
- Precise localization: no
Part #5:
- Part: Bauabschnitt
- Latitude: 51° 8' 28.6"
- Longitude: 11° 57' 45.3"
- Geodetic system: WGS84
- Precise localization: no
Update for this sheet: 11 December 2024