- City: Nußbach
- Commissioning:
- 2 turbines: Enercon E40/500 (power 500 kW, diameter 40 m)
- Hub height:
- Total nominal power: 1,000 kW
- Dismantled
- Onshore wind farm
- Developer: Juwi
Part #2:
- City: Nußbach
- Commissioning:
- 1 turbine: Enercon E66/1800 (power 1 800 kW, diameter 66 m)
- Hub height:
- Total nominal power: 1,800 kW
- Dismantled
- Onshore wind farm
- Developer: Juwi
Part #3:
- City: Nußbach
- Commissioning:
- 2 turbines: Enercon E101/3050 (power 3 050 kW, diameter 101 m)
- Hub height:
- Total nominal power: 6,100 kW
- Operational
- Onshore wind farm
- Owner:
Part #4:
- City: Nußbach
- Commissioning:
- 1 turbine: Enercon E40/600 (power 600 kW, diameter 40 m)
- Hub height:
- Total nominal power: 600 kW
- Dismantled
- Onshore wind farm
- Developer: Juwi
Part #5:
- City: Waldgrehweiler
- Commissioning:
- 2 turbines: Senvion 3.4M104 (power 3 400 kW, diameter 104 m)
- Hub height:
- Total nominal power: 6,800 kW
- Operational
- Onshore wind farm
Part #6:
- Part: Wellenberg
- City: Nußbach
- Commissioning:
- 1 turbine: Vestas V126/3450 (power 3 450 kW, diameter 126 m)
- Hub height:
- Total nominal power: 3,450 kW
- Operational
- Onshore wind farm
- Developer: Juwi