[Back to previous page]
Generalities
|
|
Details
Part #1:
- City: Cerda
- Turbine(s): (manufacturer name not available)
- Total nominal power: 900 kW
- Operational
- Onshore wind farm
- Operator: Enel GreenPower
Part #2:
- City: Cerda
- Commissioning:
- 5 turbines: Gamesa G52/850 (power 850 kW, diameter 52 m)
- Total nominal power: 4,250 kW
- Operational
- Onshore wind farm
- Operator: Enel GreenPower
Localisation
Part #1:
- Latitude: 37° 54' 12.7"
- Longitude: 13° 48' 54.5"
- Geodetic system: WGS84
- Precise localization: no
Part #2:
- Latitude: 37° 54' 36.7"
- Longitude: 13° 50' 15.3"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Update for this sheet: 16 January 2018
Complete/correct this sheet: